Wildfires, floods and earthquakes bring out contractors you've never heard of, some licensed and some not. California layers extra protections on top of the usual rules once an emergency is declared. This page covers price limits, licensing, contracts and payments for repair and rebuilding work.
Rebuilding is a home improvement
California's definition of "home improvement" includes "the reconstruction, restoration, or rebuilding of a residential property that is damaged or destroyed by a natural disaster" for which the Governor proclaimed a state of emergency or the President declared an emergency or major disaster (B&P Code §7151). So a full rebuild after a fire falls under the home improvement contract and payment rules, not new-construction practice.
The CSLB spells out what that means after the 2025 Los Angeles wildfires (CSLB Disaster Help Center):
- Fixed-price contract. Contractors must list the full agreed price and may not use "time and materials" or "cost plus" contracts for disaster-related home improvement work.
- Down payment cap. No more than $1,000 or 10 percent of the contract price, whichever is less.
- Payments follow the work. Other payments must be listed in the contract and based on work completed or materials delivered to your home.
- Right license. The CSLB tells rebuilding homeowners to verify the contractor holds a B General Building license in good standing.
These rules also apply to residential solar and accessory dwelling units, the CSLB says.
Price gouging limits
Penal Code §396 applies once the President, the Governor, or a city or county official declares an emergency.
| What | Limit | How long |
|---|---|---|
| Repair or reconstruction services, and emergency cleanup services, by a contractor | No more than 10% above the contractor's pre-emergency price | 180 days after the declaration (§396(c)) |
| Building materials, emergency supplies and most other covered goods and services | No more than 10% above the seller's pre-emergency price | 30 days (§396(b)) |
| A seller with no pre-emergency price for the item | No more than 50% above its cost | 30 days (§396(b)) |
A bigger increase is allowed only if the contractor can prove it came directly from higher costs for labor or materials, and the price is no more than 10 percent above its cost plus its customary markup (§396(c)). "Repair or reconstruction services" means work by anyone required to hold a contractor license, on residential or commercial property damaged as a result of the disaster (§396(j)(4)). Officials may extend the periods (§396(g)).
A violation is a misdemeanor punishable by up to one year in county jail, a fine up to $10,000, or both, and is also an unfair business practice (§396(h)–(i)). The Attorney General's office notes the law also applies outside the disaster area where demand rises because of the emergency (California Attorney General: Price Gouging FAQs).
Unlicensed work is a felony
Contracting without a license to repair damage from a natural disaster declared by the Governor or the President is punishable by a fine up to $10,000, imprisonment under Penal Code §1170(h) for 16 months or two or three years, or both. It can also be charged with a fine up to $1,000 and up to a year in county jail. Anyone who used the unlicensed contractor is a crime victim, whether or not they knew (B&P Code §7028.16).
Ordinary unlicensed contracting is a misdemeanor, so the disaster rule is a real step up. Check every license at the CSLB License Check, and remember the $1,000 small-job exemption never covers work that needs a permit (license rules).
Seven days to cancel
Any home improvement contract to repair or restore a home damaged by a sudden or catastrophic event with a declared state or local emergency must include a Seven-Day Right to Cancel notice. You can cancel by email, mail, fax or delivery by midnight of the seventh business day after receiving the signed contract (B&P Code §7159(e)(7)). Details on refunds are in the right to cancel guide.
Heavier penalties for payment violations
If a contractor breaks the down payment, contract-amount or payments-ahead-of-work rules in a location damaged by a declared natural disaster, the court must impose the maximum $5,000 fine (B&P Code §7159.5(b)(1)). If the violation is part of a scheme to defraud a disaster victim, the court must order full restitution and may add a fine of $500 to $25,000 based on ability to pay (§7159.5(c)).
Protecting yourself while you rebuild
- Hire a licensed contractor in the right classification. For a full rebuild, the CSLB points to a B license.
- Get more than one bid. The CSLB's tip card says at least three (CSLB 10 Tips).
- Sign a fixed-price contract with every §7159 item (contract checklist).
- Don't sign a contract or change order that requires a progress payment larger than the value of the work completed, the CSLB says.
- Collect lien releases as you pay (mechanics liens).
- Report problems. The CSLB takes reports about active rebuild job sites through its lead referral form, and complaints about contractors you hired; worker safety concerns go to Cal/OSHA (CSLB Disaster Help Center).
Price gouging can be reported to the Attorney General. For trade-by-trade price ranges to compare bids against, see the cost guides, including roofing and windows and doors.
Related pages
Sources
- California Penal Code §396
- California Business and Professions Code §§7028.16, 7151, 7159, 7159.5
- CSLB Disaster Help Center
- California Attorney General: Price Gouging During Disasters
- CSLB, 10 Tips (PDF)
- CSLB 2026 License Law and Reference Book (PDF)
Frequently Asked Questions
How long do California price gouging limits apply to contractors after a disaster?
For repair or reconstruction services and emergency cleanup, 180 days after the emergency proclamation or declaration. For most other goods and services, 30 days. State and local officials can extend the periods (Penal Code §396(c), (g)).
Is it a felony to do unlicensed contracting after a disaster in California?
It can be. Unlicensed work repairing damage from a natural disaster declared by the Governor or the President is punishable by a fine up to $10,000 and state prison of 16 months, two or three years, or as a misdemeanor with a fine up to $1,000 and up to a year in county jail (B&P Code §7028.16).
Can a contractor charge time and materials to rebuild my burned house in California?
The CSLB says no for disaster-related home improvement work: contractors must use a fixed-price contract listing the full agreed price, and may not use time and materials or cost-plus contracts. Rebuilding a home damaged in a declared disaster is a home improvement under B&P Code §7151.