California spells out what a home improvement contract must contain in B&P Code §7159 and how payments must work in §7159.5. If you know these rules, you can spot a bad contract before you sign. A contractor who leaves out required items or notices is subject to discipline (§7159(a)(5)).

When the rules apply

A "home improvement" is repairing, remodeling, altering, converting or modernizing residential property, or adding to it. It includes rebuilding after a declared natural disaster and covers driveways, pools, spas, patios, solar energy systems, landscaping, fences, garages and similar work (B&P Code §7151).

The §7159 contract rules apply when the aggregate contract price for labor, services and materials exceeds $500 (§7159(b)). Tenants are covered for work in their own unit. Service and repair contracts that comply with §§7159.10 to 7159.14 follow those sections instead (§7159(a)(2)).

Signed before work starts

  • Before any work starts, the contractor must give you a copy of the contract signed and dated by both of you. Your receipt of that copy starts your right to cancel (§7159(c)(3)(A)).
  • The contract and any changes must be in writing and signed before the covered work begins (§7159(d)).
  • Printed forms must use at least 10-point type, with some notices in 12-point bold (§7159(c)(2)).

What the contract must include

From §7159(c) and (d):

  • The contractor's name, business address and license number
  • The name and registration number of any home improvement salesperson who sold the job (salesperson rules)
  • The heading "Home Improvement"
  • The statement: "You are entitled to a completely filled in copy of this agreement, signed by both you and the contractor, before any work may be started."
  • Contract Price in dollars and cents, and any Finance Charge listed separately
  • A description of the project and of the significant materials and equipment (pools also need a scale drawing)
  • Downpayment, if any, with the bold statement that it may not exceed $1,000 or 10 percent of the contract price, whichever is less
  • A Schedule of Progress Payments in dollars and cents, each tied to specific work or materials, with the bold statement that it is against the law to collect payment for work not yet completed or materials not yet delivered
  • What counts as substantial commencement of work, an Approximate Start Date and an Approximate Completion Date
  • Any documents incorporated into the contract
  • A Note About Extra Work and Change Orders
  • A statement that, after each satisfactory payment and before the next one, the contractor will give you a full and unconditional lien release for that portion of the work
  • A notice of your right to require a performance and payment bond, near the signatures
  • Whether subcontractors will be used, with yes/no boxes (new in 2026, below)
  • On the first page: the date you signed, and the contractor's name, address and email address for sending a Notice of Cancellation, plus a phone number to help you fill it out (new in 2026)

Required notices

§7159(e) adds notices that must be in or attached to the contract:

  1. Commercial General Liability Insurance: whether the contractor carries it (with the insurer and a phone number), is self-insured, or has none
  2. Workers' Compensation Insurance: whether the contractor has no employees and is exempt, or carries it for all employees
  3. Extra work and change orders: change orders aren't enforceable against you unless they state the scope, the price change and the effect on payments or completion, in writing, before the work
  4. Mechanics Lien Warning: the statutory text explaining liens, preliminary notices and joint checks (lien guide)
  5. Information about the CSLB: including the four-year complaint deadline and the CSLB's phone number, 800-321-2752
  6. Right to cancel: the three-day notice, or five days for a buyer 65 or older, or seven days for disaster repairs, with a detachable Notice of Cancellation (right to cancel)

Payment rules

B&P Code §7159.5(a) sets the payment rules for every home improvement contract with a licensed contractor or someone required to be licensed:

Rule What it means for you
Contract amount in dollars and cents, including profit, labor and materials No open-ended price
Down payment no more than $1,000 or 10%, whichever is less On any job over $10,000, the cap is $1,000
Progress payments on a schedule tied to work and materials Each payment matches a phase
No payment beyond the value of work performed or material delivered Payments can't run ahead of the job, including advances from a lender
Lien releases on request after each payment You may withhold further payments until you get them

Violating the contract-amount, down payment or payments-ahead-of-work rules is a misdemeanor with a fine of $100 to $5,000, up to a year in county jail, or both. In an area under a declared natural disaster, the court must impose the maximum fine (§7159.5(b)).

The bonded exception. A contractor that furnishes a performance and payment bond, lien and completion bond, or bond equivalent or joint control approved by the Registrar is exempt from the down payment and progress payment limits (§7159.5(a)(8)). The CSLB notes this applies to a small number of contractors and shows on the license detail page (CSLB 10 Tips).

What changed January 1, 2026

  • Email cancellations (AB 1327). The contract must list the contractor's email address and allow cancellation by email, plus a phone number to help you locate and fill out the Notice of Cancellation. If the notice is missing, you may file a complaint with the CSLB (§7159(a)(6), (c)(3)(B)).
  • Subcontractor disclosure (SB 517). The contract must say whether subcontractors will be used. If yes, the contractor must provide, on request, each subcontractor's name, contact information, license number and classification. The same disclaimer must appear on each change order. The prime contractor is responsible for completing the project for CSLB discipline purposes (§7159(a)(5)(B), (c)(7); CSLB Industry Bulletin #25-04).

Before you sign

  • Compare the contract line by line against the list above
  • Do the down payment math yourself
  • Make sure each progress payment names the work it pays for
  • Ask for the subcontractor list if the "Yes" box is checked
  • Check the license number at the CSLB License Check

The CSLB's consumer guide to home improvement contracts, Terms of Agreement, is linked from its Disaster Help Center. For typical project prices to sanity-check a bid, see the California cost guides, such as remodeling or HVAC.

Related pages

Sources

Frequently Asked Questions

How much can a contractor ask for as a down payment in California?

No more than $1,000 or 10 percent of the contract price, whichever is less (B&P Code §7159.5(a)(3)). On a $40,000 job, that is $1,000. Contractors who file a blanket performance and payment bond approved by the CSLB are exempt from this limit.

Does a home improvement contract have to be in writing in California?

Yes, when the total price of labor, services and materials is more than $500 (B&P Code §7159(b)). The contract and every change order must be in writing and signed by both parties before the work it covers begins (§7159(d)).

Can a California contractor charge for materials before they're delivered?

No. Apart from the down payment, a contractor may not request or accept payment that exceeds the value of the work performed or material delivered (B&P Code §7159.5(a)(5)). That includes advance payment from a lender or financier.

Do I have a right to know which subcontractors my contractor uses?

Yes. Since January 1, 2026, the contract must say whether subcontractors will be used, and if so the contractor must give you a list with each subcontractor's name, contact information, license number and classification on request (B&P Code §7159(c)(7), SB 517).